Costs stack up from Metro interference on cancer centre

Electromagnetic interference from the $14 billion Metro Tunnel is still wreaking havoc on sensitive medical equipment at Melbourne's dedicated cancer centre. 

The long-running rail project will connect the busy Sunbury, Cranbourne and Pakenham lines through a new tunnel under the city and is expected to open in 2025.

But a leaked document published by The Age reveals MRI scanners at the Peter MacCallum Cancer Centre near the new underground Parkville station failed equipment tests in June.

The issue of electromagnetic interference (EMI) has reportedly cost $128 million in capital works across Peter Mac, Royal Women’s and Royal Melbourne hospitals.

Premier Jacinta Allan said EMI risks were identified from the outset of the project but the scale of the problem became clear when test trains began running through the tunnel in mid-2023.

"It was at that point that we could test the mitigation measures around the hospitals particularly," she told reporters on Wednesday.

"No patient care has been compromised."

In May, the Allan government abandoned building a medical precinct in the new suburb of Arden after technical work showed EMI from a Metro Tunnel underground station could disrupt sensitive medical equipment.

A report from the auditor-general in June stated further work was needed to address the impact of EMI at six institutions near the Parkville and State Library stations.

Peter Mac, the Royal Melbourne Hospital, Royal Women’s Hospital, University of Melbourne, Peter Doherty Institute and RMIT University were the six institutions listed.

In a temporary solution, Peter Mac moved its MRI services to its East Melbourne centre and Royal Melbourne's new MRI department.

A more permanent solution trialled involved testing magnetic active cancellation systems (MACS) to address the remaining risks on the machines at Peter Mac and the Royal Melbourne Hospital. 

The report said testing in April showed "inconclusive results" on the effectiveness of MACS and Rail Projects Victoria planned further testing for June 2024.

The Metro Tunnel was originally costed at $10.9 billion when announced in 2016 but has blown out to $12.8 billion for taxpayers and $14 billion overall.

The same auditor-general report revealed its contracted completion date of September 2024 would not be met and the state would need to pay more to address remaining issues.

Ms Allan said funding for mitigation was contained in the project's original budget but dodged questions over whether enough cash was set aside.

Opposition Leader John Pesutto said the burden of the "massive debacle" would fall on patients and taxpayers and suggested the government didn't do enough due diligence.

"You do the work before you commit to a project," he said.

License this article

What is AAPNews?

For the first time, Australian Associated Press is delivering news straight to the consumer.

No ads. No spin. News straight-up.

Not only do you get to enjoy high-quality news delivered straight to your desktop or device, you do so in the knowledge you are supporting media diversity in Australia.

AAP Is Australia’s only independent newswire service, free from political and commercial influence, producing fact-based public interest journalism across a range of topics including politics, courts, sport, finance and entertainment.

What is AAPNews?
The Morning Wire

Wake up to AAPNews’ morning news bulletin delivered straight to your inbox or mobile device, bringing you up to speed with all that has happened overnight at home and abroad, as well as setting you up what the day has in store.

AAPNews Morning Wire
AAPNews Breaking News
Breaking News

Be the first to know when major breaking news happens.


Notifications will be sent to your device whenever a big story breaks, ensuring you are never in the dark when the talking points happen.

Focused Content

Enjoy the best of AAP’s specialised Topics in Focus. AAP has reporters dedicated to bringing you hard news and feature content across a range of specialised topics including Environment, Agriculture, Future Economies, Arts and Refugee Issues.

AAPNews Focussed Content
Subscription Plans

Choose the plan that best fits your needs. AAPNews offers two basic subscriptions, all billed monthly.

Once you sign up, you will have seven days to test out the service before being billed.

AAPNews Full Access Plan
Full Access
AU$10
  • Enjoy all that AAPNews has to offer
  • Access to breaking news notifications and bulletins
  • Includes access to all AAPNews’ specialised topics
Join Now
AAPNews Student Access Plan
Student Access
AU$5
  • Gain access via a verified student email account
  • Enjoy all the benefits of the ‘Full Access’ plan at a reduced rate
  • Subscription renews each month
Join Now
AAPNews Annual Access Plan
Annual Access
AU$99
  • All the benefits of the 'Full Access' subscription at a discounted rate
  • Subscription automatically renews after 12 months
Join Now

AAPNews also offers enterprise deals for businesses so you can provide an AAPNews account for your team, organisation or customers. Click here to contact AAP to sign-up your business today.

SEVEN DAYS FREE
Download the app
Download AAPNews on the App StoreDownload AAPNews on the Google Play Store